LILAMA JSC at works of Mong Duong Thermal Power Plant
At buildings in Mong Duong 1 Thermal Power Plant, Lilama 45.1 Joint Stock Company has started constructed deployment from 25.03.2013, current the company has installation more than 3000 tons of structural steel boiler A2 and and it is expected to accomplished at the end of October 2013.
The company is installing the next item as: Installation of 7330 tonnes of boiler equipment, Installation 2306 tons of tubinne equipment, generators and 85000 ID of boiler pressure pipe... Total value of VND 180 billion.
Project of Mong Duong Thermal Power Plant 1 invested by EVN, is one of two plants of Mong Duong Power Center - development plans national electricity phase from 2006 to 2015. The plant has a total installed capacity 1.080MW (2x540MW), generator power output of 6.5 billion kWh annually. Mong Duong 1 Thermal Power Plant was built in Zone 3, Mong Duong ward, Cam Pha town, Quang Ninh province.
Lilama 45.1 is one member of Lilama contractors - The general contractor Hyundai Engineering and Construction Co., Ltd. (South Korea) undertake all the items from the design, supply, installation commissioning, operation and maintenance with contract worth U.S. $ 1,274 billion. As planned, unit 1 will be completed and operation after 40 months ( quarter 1 of 2015) and units 2 will be operation after 46 months (estimate quarter III of 2015).