No. |
Tên |
Thời gian |
Khách hàng |
Phạm vi công việc |
1 |
Long Phu 1 thermal power plant |
01/2017 - 2018 |
LILAMA / PVN |
Material erection (piping system, steel structure & accessory) for boiler Unit 1. |
2 |
Ho Chi Minh anti-flood |
02/2017 - 2018 |
Trung Nam Group / LILAMA 45.3 |
Manufacture and erection of mechanical equipment |
3 |
First Solar Project |
08/2017 - 2018 |
Shinryo Vietnam Corporation |
CDA (Compressed Dry Air) & PCW (Process Cooling Water) work, insulation works for PCW pipe, equipments installation work for PCW system |
4 |
Nghi Sơn Oil Refinery, Thanh Hoa Province |
2014-2017 |
LILAMA Corporation/SK E&C |
Fabrication of spool and erection of pipe, tanks |
5 |
Vinh Tan 4 Thermal Power Plant |
06/2015 - 2017 |
Doosan Heavy Industries Vietnam Co., Ltd. / LILAMA |
Installation of circle water pipe, boiler steel structture |
6 |
Vinh Tan 4 Thermal Power Plant |
06/2015 - 2017 |
Doosan Heavy Industries Vietnam Co., Ltd. / LILAMA |
Installation of equipments: boiler pressure parts, boiler piping, boiler non-pressure parts. |
7 |
Vinh Tan 4 Thermal Power Plant |
12/2015 - 2017 |
Doosan Heavy Industries Vietnam Co., Ltd. / LILAMA |
Installation of BOP system |
8 |
Vinh Tan 4 Thermal Power Plant |
03/2016 - 2017 |
Doosan Heavy Industries Vietnam Co., Ltd. / LILAMA |
Installation of equipment for electrical, instrument & control system unit 1 |
9 |
Vinh Tan 4 Thermal Power Plant |
11/2016 - 02/2017 |
Bao Chi Lam JSC |
Construction of water and electrical work |
10 |
Vinh Tan 4 Thermal Power Plant |
05/2016 - 2017 |
Doosan Heavy Industries Vietnam Co., Ltd. / LILAMA |
Installation of Coal Shed |