Installation of Stator Frame Unit #1 288 tons at Song Hau 1 Thermal Power Plant

                            

In the Morning (20/4), at Chau Thanh Town, Hau Giang Province, Erection Team No.3, Lilama 45.1 Joint Stock Company  has cooperated with related units to successfully installation Stator No 1 of Song Hau 1 Thermal Power Plant Project


Stator set no. 1 weighs about 288 tons, capacity of 727,100 kVA, voltage 22,000 V, provided by Doosan (South Korea). The Stator will be raised to 18m and moved 70m in the turbine compartment. It takes 10 hours for the transmitter to move to the installation position.



 

 

 