Technological and Pressure Pipe Project


The Piping System of Heat Recovery Steam Generator for Thermal Power Plants

 Project: Group of The Phu My Thermal Power Plant


 OwnerVietnam Electricity Corporation (EVN); Mekong Energy Co.(MICO); British Petroleum Holding BV, Semb Corp Ultilities (Singarpore) and group of contractor including Kyushu Electric Power Co., Inc and Nissho Iwai (Japan)


 ClientMitsubishi, Marubeni, Alstom, Taihei Dango Kaisha


 Installation location: Group of The Phu My Combined Cycle Power Plant (1, 2-1, 2-2, 3, 4) and Phu My 2-1 Entension Add-On Combined Cycle Power Plant


 Year completed: 2006 ÷ 2008 

Circulation Water Piping for Hydropower Plants

 Project: Dai Ninh Hydropower Plant


OwnerVietnam Electricity Corporation (EVN)


Client: HITACHI Corporation


Installation locationDai Ninh Hydropower Plant, Lam Dong Province


Year completed: 2006



+ Diameter of the pipeline: 3.2 - 3.3 m

+ Length of the pipeline: 1,818 km

Pipeline Fuel (petrol, oil, gas, etc.)

 Project: Nam Con Son Pipeline


 Owner: Petro Vietnam Gas Corporation (PV Gas)


 Client: MC Connel Dowell


  Installation location: Dinh Co Gas Processing Plant, Ba Ria - Vung Tau Province


 Year completed: 2002



+ Length of pipe: 370km

+ Diameter: 26 inches, kind of two-phase pipe

+ Transport capacity: 19.8 million m³ gas/day (approximately 7 billions m³ gas/year)

 Stack of Thermal Power Plant
   Project: Nhon Trach 1 Combined Cycle Power Plant (462,8 MW)


 Owner:  Viet Nam National Oil and Gas Group 




 Location:  Phuoc Khanh Village, Nhon Trach District, Dong Nai Province


 Year Completed: 2011



 Inside Diameter of Stack: 6.5m

 Elevation (Top of Stack): 60m